In 2022 has begun initiative for installing of photovoltaic panels on roof construction in TE-TO power plant. At the end of 2022 has started installation of photovoltaic system, as a pilot project, on ST hall roof.

 

Photovoltaic system is consist of 88 panels, 550W power each panel, and total maximum power of 48kWp and 40kW three phase inverter.

Photovoltaic system is connected to plant home consumption busbar and it is using for power plant needs. Photovoltaic system commissioning has been performed during planed outage in May 2023.