TE-TO AD Skopje on 21.05.2021 successfully completed the first C Inspection of the gas turbine, type GT13E2, production of GE Power, which is a capital investment for this type of power plants.
In the next few days, the operation of the entire plant will be tested, in different operating modes, in order to optimize the parameters of all systems, which will enable further reliable supply of electricity and heat to the local and regional market.
The tests according to the plan should finish on 27.05.2021 and then the power plant should continue with commercial operation.